- Contract amount: 19 475 928.095 TND
- Work execution time: 20 months
- Client: Ministry of Housing Equipment and Regional Planning
Consistency of the work
1 Bridge made up of 2 decks with prestressed concrete beams
5 Reinforced concrete structures
Deviation from dealer networks
The main quantities
Landfill or landfill: 180,000 m3
Loan for backfill: 160,000 m3
Grave bitumen: 35,000 m3
Bituminous concrete: 13,600 m3
Concrete: 18,000 m3
Concrete reinforcement: 1,383,000 Kg